Campus capacity
800 MWThree halls; up to 600 MW IT disclosed
Independent project intelligence · Updated 1 Oct 2026
A public-source view of the proposed AI infrastructure campus and the energy system that must make it possible.
01 / Project snapshot
IREN has selected Bundey for its first announced Australian data centre campus—one of the largest proposed in the Asia-Pacific region.
A federal environmental referral now provides a preliminary concept: three data halls, a 610.4-hectare project area, dedicated bulk and primary substations, and a progressive six-to-eight-year build. The connection is secured; the final design, state approval pathway, customer mix and energy procurement structure remain unresolved publicly.
Read the federal referral ↗Confirmed parameters
Confirmed Reported / pendingThree halls; up to 600 MW IT disclosed
565.2 ha campus + 45.3 ha corridor
Bulk and primary substations disclosed
Progressive program in EPBC referral
IREN estimate
During progressive initial fill
02 / Two linked systems
The former “Data Centre / Power Systems” split is reframed as Compute Campus and Energy & Utilities: clearer language for both technical and public audiences.
COMPUTE CAMPUS
Hyperscale halls, AI compute, cooling, fibre, security and campus delivery.
ENERGY & UTILITIES
Grid connection, firmed renewable supply, water, backup generation and network impact.
Indicative geography—not a navigation or engineering map. Climate figures are long-term regional averages, not a site forecast.
03 / Why Bundey
Bundey’s strategic advantage is its proximity to major transmission infrastructure. The trade-off is a regional delivery environment well beyond Adelaide’s labour, freight and specialist-services base.
04 / Energy pathway
Important distinction: an 800 MW transmission connection is not, by itself, proof of 800 MW of new renewable generation or firming.
05 / Environment & community
IREN states that progressive initial fill will require about 3 ML every six months, followed by annual maintenance top-ups below 1% of system capacity. Heat-rejection design and complete site water demand remain to be verified.
IREN community information ↗Track the additional generation, firming, certificates, network services and demand flexibility required to offset the new load without transferring cost or reliability risk.
AEMC policy advice ↗EPBC referral 2026/10605 covers 610.4 hectares and identifies vegetation, habitat, water, noise, backup generation and transmission works for assessment. The state approval position remains separately tracked.
Federal referral ↗06 / Rolling timeline
07 / Who is IREN
Founded in Sydney in 2018 by brothers Daniel and Will Roberts, the company began as Iris Energy, building renewable-powered Bitcoin mining operations. It listed on Nasdaq in 2021 and rebranded as IREN in 2024 as it expanded into AI cloud and data centres.
08 / Latest project coverage
Short summaries link to the original record. Inclusion does not imply endorsement.
The EPBC referral discloses the preliminary campus footprint, electrical architecture and a six-to-eight-year construction program.
Read source ↗IREN states 3 ML per six months during progressive cooling-system fill and commits A$250,000 annually to community grants.
Read source ↗FY26 results place Bundey within IREN’s global 5+ GW pipeline; no Bundey customer, funding structure or delivery model was disclosed.
Read source ↗09 / Editorial monitoring
This first release defines the monitoring model. Live scheduled scanning needs source connectors and will be activated separately.
Open restricted briefing ↗Planned: preset weekly scan · manual trigger · retain / reject queue · change log · source confidence.