Independent project intelligence · Updated 1 Oct 2026

IREN Bundey
Data Centre Campus

A public-source view of the proposed AI infrastructure campus and the energy system that must make it possible.

800MWPlanned campus load
2028Target first energisation
610haFederal referral project area
6–8yrProgressive construction
PROJECT STATUSFederal EPBC referral lodgedState development-approval status not yet verified
Explore the snapshot ↓

Compute meets
clean energy.

IREN has selected Bundey for its first announced Australian data centre campus—one of the largest proposed in the Asia-Pacific region.

A federal environmental referral now provides a preliminary concept: three data halls, a 610.4-hectare project area, dedicated bulk and primary substations, and a progressive six-to-eight-year build. The connection is secured; the final design, state approval pathway, customer mix and energy procurement structure remain unresolved publicly.

Read the federal referral ↗
Confirmed   Reported / pending
01

Campus capacity

800 MW

Three halls; up to 600 MW IT disclosed

02

Project area

610.4 ha

565.2 ha campus + 45.3 ha corridor

03

Grid interface

330 / 132 / 33 kV

Bulk and primary substations disclosed

04

Construction

6–8 years

Progressive program in EPBC referral

05

Employment

500+ build / 200+ ongoing

IREN estimate

06

Cooling water

3 ML / six months

During progressive initial fill

One project.
Two delivery tests.

The former “Data Centre / Power Systems” split is reframed as Compute Campus and Energy & Utilities: clearer language for both technical and public audiences.

A

COMPUTE CAMPUS

The digital infrastructure

Hyperscale halls, AI compute, cooling, fibre, security and campus delivery.

  • Scale: 800 MW planned campus capacity
  • Market: regional and global AI workloads
  • Cooling: sealed closed-loop design reported
  • Open: phases, PUE, vendors, customer contracts
Primary source ↗
B

ENERGY & UTILITIES

The enabling infrastructure

Grid connection, firmed renewable supply, water, backup generation and network impact.

  • Connection: Bundey 275/330 kV substation
  • Capacity: four 330 kV feeder exits reported
  • Policy: new renewables + firming under scrutiny
  • Open: who funds, owns, builds and operates supply
Project EnergyConnect ↗
Bundey site logistics within South AustraliaA simplified outline map showing Bundey, Robertstown, Adelaide, Port Adelaide and the Project EnergyConnect transmission corridor.PROJECT ENERGYCONNECT · 330 kV CORRIDORNEW SOUTH WALESBUNDEYPROPOSED 800 MW CAMPUSROBERTSTOWNNEAREST TOWNSHIP · ≈15 KM SWADELAIDE≈125 KM SW OF BUNDEYPORT ADELAIDESOUTH AUSTRALIASIMPLIFIED LOGISTICS VIEWN
Project siteTransmission corridorPrimary logistics route
Seasonal operating contextEudunda climate averages · nearest long-record BOM station
BOM station 024511 ↗
Monthly average high and low temperatures and rainfallEudunda long-term climate averages by month, used as a regional proxy for Bundey.10°20°30°30°29°26°22°17°14°13°15°17°21°25°27°14°14°12°10°8°6°5°5°7°8°10°13°JAN22FEB22MAR21APR33MAY45JUN52JUL51AUG55SEP48OCT40NOV31DEC26AVG HIGH °CAVG LOW °CMM

Indicative geography—not a navigation or engineering map. Climate figures are long-term regional averages, not a site forecast.

Grid-connected.
Logistically remote.

Bundey’s strategic advantage is its proximity to major transmission infrastructure. The trade-off is a regional delivery environment well beyond Adelaide’s labour, freight and specialist-services base.

01Approximately 125 km north-east of Adelaide and its metropolitan workforce base
02Robertstown is the nearest township, approximately 15 km south-west, with limited local services
03Port Adelaide is the principal import gateway, requiring freight staging and heavy-haul planning
04Direct proximity to the Project EnergyConnect transmission corridor is the decisive site advantage

Connection secured.
Supply model unresolved.

Important distinction: an 800 MW transmission connection is not, by itself, proof of 800 MW of new renewable generation or firming.

01Renewable generationExisting + proposed projects
→
02Firming & storageBESS / dispatchable capacity
→
03Bundey substation275 / 330 kV interface
→
04Compute campusUp to 800 MW load

Track the questions,
not just the claims.

WATER

Closed loop, now quantified

IREN states that progressive initial fill will require about 3 ML every six months, followed by annual maintenance top-ups below 1% of system capacity. Heat-rejection design and complete site water demand remain to be verified.

IREN community information ↗
ENERGY

Net renewable is a system question

Track the additional generation, firming, certificates, network services and demand flexibility required to offset the new load without transferring cost or reliability risk.

AEMC policy advice ↗
APPROVALS

Federal referral now public

EPBC referral 2026/10605 covers 610.4 hectares and identifies vegetation, habitat, water, noise, backup generation and transmission works for assessment. The state approval position remains separately tracked.

Federal referral ↗

IREN lists on Nasdaq as Iris Energy

Company milestone

Project EnergyConnect and the new Bundey 275/330 kV substation advance

Enabling infrastructure

IREN announces signed transmission connection agreement

Confirmed

Federal EPBC referral process commences

Referral 2026/10605

IREN holds regional community drop-in sessions

Community engagement

Target commencement of campus energisation

Forward target

From Bitcoin
to AI infrastructure.

Founded in Sydney in 2018 by brothers Daniel and Will Roberts, the company began as Iris Energy, building renewable-powered Bitcoin mining operations. It listed on Nasdaq in 2021 and rebranded as IREN in 2024 as it expanded into AI cloud and data centres.

NASDAQ IRENLEADERSHIP Daniel Roberts & Will Roberts, co-CEOsOWNERSHIP Publicly traded; founders retain significant influenceBUNDEY TEAM No dedicated IREN project team publicly named
IREN MARKET DATAView live share price and filings↗

Signal, compacted.

Short summaries link to the original record. Inclusion does not imply endorsement.

A controlled update workflow.

This first release defines the monitoring model. Live scheduled scanning needs source connectors and will be activated separately.

Open restricted briefing ↗
Source monitorWORKFLOW PREVIEW
Project announcementsManual approval
REVIEW
Energy & gridAuto-publish confirmed facts
AUTO
Environment & communityManual approval
REVIEW
Market & companyAuto-publish links only
AUTO

Planned: preset weekly scan · manual trigger · retain / reject queue · change log · source confidence.